Site
Brussels Airport

Year
13/07/2020 – 19/08/2020

Client
Brussels Airport Company

Project Description
At the airport of Zaventem runway 07L/25R was renovated.  This is the most widely used runway in our country, so this renovation can rightly be called a prestige project.  By the way, this is the third time that Mobix has been involved in such renovation projects at the airport, so that proves once again the expertise of our people at Tel&Sec!

 

What does this project mean for Mobix?

- Pulling +/- 120 km of primary cabling ( beaconing )

- Laying +/- 165 km of secondary cabling. ( beaconing )

- Replacement of +/- 2000 light beacons.

- Execution of 6 controlled drillings of +/- 100m long.

- Installation of a completely new approach (concrete pedestals, poles, lights, cabling etc. ).

 

These works were carried out by about 140 workers between 13/7/20 and 19/08/20, in 6 phases including some night phases.